Update status of task:
Description of task:Power failure - Circuit breaker flips (labeled UPS in). See attached image.

Updated by
(Re)assign to
New status
Comment
Expected handled on Expected to be handled on? [YYYY-MM-DD]


Old comments:

2025-01-09 23:39: [Mads]: The dome slit (upper part) was closed by hand using the metal handle by Rosa and night assistant

2025-01-09 22:35: [Mads, Rosa (support ast)]: Power failure happened while I was checking for light through the whole system; dome open, telescope tracking. When Rosa flipped power on it started powering on things but after a while it flipped again. A propper check of the electrical system is needed. Something is not well on the power grid.